Week of 02-27-2019 to 03-06-2019
I was able to finalize my design this week and plan to start machining at makerspace very shortly. Additionally, I received my springs and brake material this week from Mcmaster Carr. I will be purchasing my aluminum stock from Campbell Metals today. By Friday 03/08/2019, I will have 90% of my parts for my design. The other 10% are misc hardware that can be purchased from Homedepot and Dale Hardware. I plan to have my design built by late March/ Early April.